Frequently Asked Questions

The Need

Why does the school need a new HVAC system?

The school's primary boilers were installed in 1960 and 1971, and many classrooms currently rely on window air conditioners and mini-split units. The proposed project would replace this aging equipment with a modern geothermal system.

Why not simply repair or replace the existing equipment?

Repairs can keep aging equipment operating, but they do not address the limitations of the overall heating and cooling system. The district also reviewed replacing the existing system with new conventional equipment. That option would require replacing the entire system—not just the physical boilers—and the estimated cost was close to the proposed geothermal system.

Unlike the geothermal project, however, the conventional replacement option would not be eligible for the available federal tax credits. The proposed geothermal system would replace the aging, separate systems with a centralized heating and cooling solution and qualify for federal incentives that can offset a portion of eligible project costs.

Why pursue the project now?

In addition to the age of the existing equipment, the district estimates that the project could qualify for more than $2 million in federal tax credits. The district's fact sheet states that delaying the project would mean permanently forfeiting those anticipated savings.

What happens if the bond does not pass?

The existing 1960 and 1971 boilers would remain in service. The district anticipates increasing failure risk and maintenance costs, and the estimated $2 million-plus in federal tax credits would be forfeited. The district also projects that replacing the system later could cost more and potentially require a higher property tax rate.

How does the current portion of the building served by geothermal perform vs. the portion served by boilers?

Temperatures differ between those areas, especially during the “shoulder” seasons.

About the Proposal

What is geothermal, and why was it selected?

Geothermal uses water circulated through the ground to exchange heat, allowing equipment within the building to provide heating or cooling as needed. Lone Tree already has experience with this technology: portions of the school have been served by geothermal since 2002.

How would the project benefit students and staff?

The project is designed to provide more consistent year-round temperatures, reliable heat during Iowa winters and dependable air conditioning during hot early-fall weather. The district also expects the new system to improve comfort and learning conditions.

Would the project improve classroom air quality?

During the facility walkthrough, staff explained that some existing classroom equipment does not introduce fresh outside air. The proposed system would provide fresh-air ventilation and allow CO₂ levels to be monitored within spaces.

Would the new system reduce operating costs?

The district expects the geothermal system to be significantly more energy efficient. Its facilities plan anticipates lower long-term energy costs, which would free district resources for instruction.

Has the district used geothermal before?

Yes. An existing geothermal system has served portions of the building since 2002. The proposed project would expand geothermal to provide building-wide heating and cooling.

What is the lifespan of the geothermal systems?

While the general lifespan of heat pumps is around 30 years, the warranty of the geothermal field loop piping is 50 years based on the manufacturers’ non-prorated warranty per our specifications.

Who will maintain the geothermal system? 

Shared Operations Director Mike Klinkkamer and Director of Buildings & Grounds Scott Feldman will maintain the geothermal system.

About the Bond

How much would the project cost?

The total project cost is estimated at $6.9 million.

Would the bond increase the school property tax rate?

The district projects no increase to the current school debt levy tax rate. Because the Wellness Center bond is nearing completion, the district can finance the proposed project while maintaining the current rate. The projected rate is $12.78 per $1,000 of assessed value.

How long will the bond last? Can it be paid off early?

The final repayment schedule will be established when the bonds are issued. While the bonds may be structured with a longer repayment period, the district may have opportunities to pay down the debt sooner, depending on the final bond terms and available district funds.

One option the Board could consider is using proceeds received from the federal tax credits to help pay down the bond debt. The geothermal project is currently estimated to qualify for approximately $2 million in federal tax credits. Once those funds are received, the Board would have the option to consider applying them toward the debt, which could shorten the repayment period and reduce future interest costs.

Any decision to pay bonds early would be made by the Board based on the bond terms, the district’s financial position, and applicable requirements at that time.

Is this bond proposal tax neutral?

The bond proposal is tax neutral. With the Wellness Center bond nearing completion, the Lone Tree CSD can finance this project without increasing the current school debt levy tax rate.

What if project costs increase with unforeseen issues?

The district has two other options for funding facilities: PPEL and SAVE.

When is Election Day?

The bond referendum is scheduled for November 3, 2026.

About Planning and Construction

How would construction affect students?

Construction would be completed in phases to minimize disruption to students and staff. The district's plan is to keep classrooms open and learning on track throughout the project.

When would construction happen?

If the bond passes, the current timeline calls for project bidding and award in 2027, followed by phased classroom construction and project completion in 2028.

How long has the district been planning this project?

This proposal is part of a multi-year facilities planning process. The district conducted an HVAC study in 2023, completed South Gym HVAC work in 2024, reviewed and refined options in 2025, and continued design and cost analysis in 2026.

What do you expect for change orders?

Typically, 5%, but Shive-Hattery’s goal is 1-2% or less based on geothermal project experience.

Bottom line, change orders on a CMaR project technically can’t result in a project cost beyond the guaranteed maximum price (i.e. the GMP is the GMP). Percentages are based on experience and are corroborated by an AIA study.